The City of San Clemente is beginning Pier Plank Replacement Monday April 25 2016.

The City of San Clemente will begin replacing planks on the San Clemente Municipal Pier in front of the Fisherman’s Restaurant.

The City has contracted with Bellingham Marine Industries, Inc. to perform this work, which is expected to take approximately one month to complete construction.

The work will consist of removing and replacing planks from the pier head (asphalt section) to about five feet beyond the restaurant balconies.

Working hours will be from 8:00 a.m. to 4:30 p.m. Monday through Friday.

During construction, the contractor will provide a pedestrian access bridge for public traffic at all times.

Only very brief 15-minute closures are anticipated during the time the contractor relocates the bridge to follow the limits of the work area as the sections are completed.

If you have any questions regarding this upcoming work

please call Amir Ilkhanipour, Sr. Civil Engineer at (949) 361-6140.